Required occupation times

  • 1.  Required occupation times

    Posted 08-26-2019 19:07

    With regards to the Trimble Catalyst RTK service, how long do you have to remain at a position to achieve the stated accuracy levels? In other words, what are the occupation times necessary for meter/submeter/10 cm/1-2 cm accuracy levels? 

     

    Rudy Stricklan, RLS



  • 2.  RE: Required occupation times
    Best Answer

    Posted 09-14-2021 09:26
    Hi Rudy

    Take a look at the Positioning Performance section of the DATA SHEET HERE for the typical time to first fix (TTFF) for the various subscription accuracy levels we offer



    ------------------------------