I would like to put in a request for a macro to copy linework with an option to create new layers by adding a prefix to the lineworks' current layer and the option to set a layer group. All of the other layer properties can stay they same.The use for this is way doing phase worked and some temporary construction where a model is being built about other existing data.
What I envision:
- Selection: window selection for entities to copied
- Option: Prefix to be added to newly created layers (If I input Ph1-, I will get new layers showing PH-1-3D-Break, PH1-3D-EP)
- Option: to set layer group for new layers created (Phase 1, Phase 2)
Please let me know if you have any questions on this. Thank you.
I added a TML called CopyLayerGroupMembers. See if that does what you want.