AnsweredAssumed Answered

Site Improvements cannot be stacked.  Example being a base course that extends 6” beyond the pavement surface has to be a separate site improvement and manually added to the pavement surface site improvement to get total base course for the roadway.

Question asked by Travis Infinger on Jan 3, 2019
Latest reply on Jan 4, 2019 by Alan Sharp