Mapping and GIS Solutions Community

 View Only

Total Station Resection - Minimum Points Required

  • 1.  Total Station Resection - Minimum Points Required

    Posted 07-16-2025 07:05
      |   view attached

    Morning

    Recently updated our access to the version 2025.10 on a TSC6

    Previously we were able to position our total station using a minimum of 2 GNSS observation, this would bring up the resection results page and have the option to add additional points, change to 1D, 2D  etc

    Since updating to 2025.10 access now decides which points to use, forcing a minimum of 3 points, sometimes up to 5, will only use 2 of them and can be the points with the worst geometry / residuals. 

    Ive attached an image from a site team showing 5 points required, from this screen we are unable to change which of the points it uses, even pressing 'use' does not change anything, you cannot change 1D 2D.  

    Is there any way of changing this to how it used to be, or being able to see the tolerances that access it using to decide which points are used?

    Cheers 

    L



    ------------------------------
    Laurence Washbrook
    ------------------------------