Reassign Work Orders in Works Manager

  • 1.  Reassign Work Orders in Works Manager

    Posted 25 days ago

    What is the correct way to reassign a work order from one data collector to another in a WorksManager project?



    ------------------------------
    M Hufford
    ------------------------------


  • 2.  RE: Reassign Work Orders in Works Manager

    Posted 24 days ago

    Hello Hufford,

    Currently, WorksManager does not support reassigning a work order from one data collector to another.

    This functionality is not available at this time.



    ------------------------------
    Madhavan B
    ------------------------------



  • 3.  RE: Reassign Work Orders in Works Manager

    Posted 24 days ago

    Transferring work orders is the only reason I still use TCC.  We need the ability to share/move work orders in WorksManager before TCC is retired.



    ------------------------------
    Jason Smyth
    ------------------------------



  • 4.  RE: Reassign Work Orders in Works Manager

    Posted 23 days ago

    Hello Jason, thank you for the feedback. In this quarter, we are working to bring in the option to upload/ download/ delete/ copy/ move folders in the WorksManager file explorer view. Though we don't intend to replace TCC explorer as a standalone tool, we believe this functionality would help you manage work orders better. Let us know if there are any other TCC related needs. We will be happy to get in touch with you for a discussion.



    ------------------------------
    Vijay Raghunathan
    ------------------------------



  • 5.  RE: Reassign Work Orders in Works Manager

    Posted 23 days ago

    I'm not sue of the official recommended way, but we do one of the following:

    • Using TCCexplore, we move all the work orders to the new controller.  Make sure the new controller is assigned in WM and has performed an initial sync.   Work orders should always be moved and not duplicated and should remain unique to each controller.
    • In field using USB stick if both controllers are present.  This is done by our data prep team remotely using TeamViewer.
    • Without a USB stick this can be done in TeamViewer through its file transfer feature.

    The new features Vijay mentioned will be a great improvement.



    ------------------------------
    Matt Eklund, PE
    GPS Program Manager
    Sukut Construction
    California, USA
    ------------------------------



  • 6.  RE: Reassign Work Orders in Works Manager

    Posted 18 days ago

    Why share WO#s?  I interested to see why there is a need to share WO#s.  



    ------------------------------
    Francisco Guerrero
    ------------------------------



  • 7.  RE: Reassign Work Orders in Works Manager

    Posted 18 days ago

    That would be a slightly different question from this thread, which would like to move work orders from device to device.   To answer your question about sharing work orders, it would be helpful, for example, in tracking as-builds if there was an option to make the work order collaborative so that all grade checkers can see the work of others.  Right now we have to make sure that all "remedial shots" are taken on the same rover.  It makes it easier to post process in the office when you don't have to chase shots all over different work orders and different controllers.



    ------------------------------
    Matt Eklund, PE
    GPS Program Manager
    Sukut Construction
    California, USA
    ------------------------------



  • 8.  RE: Reassign Work Orders in Works Manager

    Posted 18 days ago

    Collaborative work orders would be top-notch! We have been mentioning it to Trimble for years, but I've never heard Trimble seriously consider the concept.



    ------------------------------
    M Hufford
    ------------------------------



  • 9.  RE: Reassign Work Orders in Works Manager

    Posted 15 days ago

    That would be an excellent feature if you could share work orders or have a "master" that is shared between devices. Tracking down data and piecing as-builts together especially on those bigger projects has always been a challenge.



    ------------------------------
    Steve Lloyd
    ------------------------------