TILOS

 View Only

 [BASELINE] Reverting Schedule Back to Either Previous or Any Baseline of Choice

Adriann Adriano's profile image
Adriann Adriano posted 04-21-2026 17:59

Hello TILOS users,

I have been playing around with the Baseline Manager and task progressing on TILOS 11.1 MR4 and I was wondering how I can revert back to the original schedule? I created a baseline for the original schedule and then added distance-split to one of my tasks which then I rescheduled to move tasks with no progress to after the date line. The only way I could think of other than undoing is to manually delete the part of the task with progress and edit the tasks with no progress to their original state.

Is there any way to revert it back to the original schedule or at least to the previous baseline?