Hi,
I linked a TILOS schedule to Trimble Connect and then reviewed the tasks in the Organizer. I noticed discrepancies in the schedule data after the import.
Specifically:
- All Start Dates in Trimble Connect are one day earlier than in TILOS.
- The Duration values are also incorrect for all tasks.
For example, I have a task in TILOS with the following properties:
- Start Date: 14.03.2028
- End Date: 12.05.2028
- Duration: 56 working days
After importing to Trimble Connect, the same task appears as:
- Start Date: 13.03.2028
- End Date: 12.05.2028
- Duration: 18 days 16 hours
Has anyone encountered a similar issue when importing schedules from TILOS to Trimble Connect?
Any advice would be appreciated. Thank you!