TILOS

 View Only

 TILOS & Trimble Connect – Incorrect imported data

Natalya Shin's profile image
Natalya Shin posted 06-26-2026 05:29

Hi,

I linked a TILOS schedule to Trimble Connect and then reviewed the tasks in the Organizer. I noticed discrepancies in the schedule data after the import.

Specifically:

  • All Start Dates in Trimble Connect are one day earlier than in TILOS.
  • The Duration values are also incorrect for all tasks.

For example, I have a task in TILOS with the following properties:

  • Start Date: 14.03.2028
  • End Date: 12.05.2028
  • Duration: 56 working days

After importing to Trimble Connect, the same task appears as:

  • Start Date: 13.03.2028
  • End Date: 12.05.2028
  • Duration: 18 days 16 hours

Has anyone encountered a similar issue when importing schedules from TILOS to Trimble Connect?

Any advice would be appreciated. Thank you!