 Duration format in the Gantt chart

Georgi Ivanov's profile image
Georgi Ivanov posted 11-20-2023 01:15

Dear Community,

What can I do in order to show the duration in the Gantt chart in calender days or even better in the days of the task calender? Most of the works I have are 24/7 with few holiday breaks.

I unfortunately do not find any suitabble option.

Enclosed you find what I currently get as result and what I found as option for the duration

It looks as it counts the number of 8-hour shifts within the period of the works. 

Thank you very much,

Georgi

Ralph Waugh's profile image
Ralph Waugh

Hi Georgi.

Did you define the respective calendar's "BASISZEITEINHEIT"?

You can choose a unit, define it's "working minutes" and decimals.

Kind regards
Ralph
Georgi Ivanov's profile image
Georgi Ivanov

Thank you @Ralph Waugh,

My "Basiszeiteinheit" is AT and AT has 1.440 minutes.

Unfortunately somehow I get the unit AT (8h) as value for the Gantt Chart Column. In the task calender I have also 1.440 minutes.

Georgi

Thorsten Jourdan-Balthasar's profile image
Thorsten Jourdan-Balthasar

In the Dialog above, go to the Darstellung tab.
There you can set the time unit for this column in Gantt.

regards

Thorsten