Dear Community,
What can I do in order to show the duration in the Gantt chart in calender days or even better in the days of the task calender? Most of the works I have are 24/7 with few holiday breaks.
I unfortunately do not find any suitabble option.
Enclosed you find what I currently get as result and what I found as option for the duration
It looks as it counts the number of 8-hour shifts within the period of the works.
Thank you very much,
Georgi
Hi Georgi.
Did you define the respective calendar's "BASISZEITEINHEIT"?
You can choose a unit, define it's "working minutes" and decimals.
Thank you @Ralph Waugh,
My "Basiszeiteinheit" is AT and AT has 1.440 minutes.
Unfortunately somehow I get the unit AT (8h) as value for the Gantt Chart Column. In the task calender I have also 1.440 minutes.
In the Dialog above, go to the Darstellung tab.There you can set the time unit for this column in Gantt.
regards
Thorsten