Trimble Business Center

 View Only
Expand all | Collapse all

Append Vertical Alignment from another Vertical ALignment...

  • 1.  Append Vertical Alignment from another Vertical ALignment...

    Posted 09-12-2018 10:40

    This is vertical A in Alignment editor...

    When I create a new alignment and append the vertical with A, I get this.....

    The program adds in the PVC and PVT locations.... 

     

    Any advice on how to avoid getting the PVC and PVT?



  • 2.  Re: Append Vertical Alignment from another Vertical ALignment...

    Posted 09-13-2018 13:31

    Are you getting an elevation shift because of the values added?



  • 3.  Re: Append Vertical Alignment from another Vertical ALignment...

    Posted 09-18-2018 04:59

    It does not appear to be any difference in vertical alignments other than adding the VPC and VPT as grade breaks for every VC.



  • 4.  Re: Append Vertical Alignment from another Vertical ALignment...

    Posted 09-24-2018 17:13

    Why are the Grade Breaks a problem at the VPC / VPT locations - basically when you append a VAL to a Vertical alignment it is adding those lines because they are actually Grade Breaks in the source VAL (because they are where the Line element joins the vertical curve element. Because they are accurately computed they will not cause you any issue and the Math is working because no Error Flags are shown in the VAL itself - so this will have zero effect on the Vertical Alignment in BC-HCE or as an outflow to SPS or GCS / Earthworks. Is this causing you an issue with output to other Field systems

     

    If Yes then you can delete the unnecessary rows (select the Row, Right Click and Delete it) - while this is extra work we dont actually know whether the VAL was created in BC-HCE or in a third party software at this stage - so we just recreate all of the node that are defined in the VAL because we cannot just kick out Grade Breaks because many alignments do have Grade Breaks in the Alignment that would be necessary and we don't actually know that they are the VPC / VPT poiints (and since it has no affect on Trimble Systems we have not worried about addressing that.

     

    Let me know if this helps - I will forward to Dev Team but I dont think that this is a High Priority Fix or necessary for at least Trimble workflows at this stage - can you advise why this is an issue (other than Cosmetics and extra data lines in the VAL editor)

     

    Alan



  • 5.  Re: Append Vertical Alignment from another Vertical ALignment...

    Posted 10-01-2018 03:58

    Agreed that it is not of high priority and there is no mathematical error present. It is simply an issue of extra work if it becomes necessary to edit the VAL. However, it makes more sense when you explain how the program is reacting in terms of importing data from other software. Thanks!!