Thanks for the clarification, Antti! I will work with engineering to add a cost code field and add that information to a simple Excel type report.
Original Message:
Sent: 02-22-2022 00:15
From: Antti Niittyoja
Subject: TBC Material and Site Improvement (MSI) Manager external data
Hi Charlie!
Unfortunately those codes are our customers company's own material codes and I am not allowed to share them.
They would like to add a code for every material so it would be easier to handle all the data in all softwares.
For example they have a construction site and one part of it is Earthmoving.
They have list as .csv of all materials and codes they want to use.
(material)Asphalt AB22,(code)A12345,(volume)m³
(material)Grass rolls,(code)A67890,(volume)m²
etc.
They want to do all site takeoffs and planning and when they are ready they want to
export that data in custom format in .csv which would look the same as import:
Asphalt AB22,A12345,1430m³
Grass rolls,A67890,670m²
They use the A12345-codes in their other programs where they calculate also
other costs like building materials and they have database where all the latest
prices are.
I believe importing that list is not so critical because codes can be added to the material name in MSIM
Asphalt AB22/A12345 and they create a site takeoff report and in Excel they create a macro to separate the name and the code
when exporting.
I believe it would be really handy to have possibility to create full custom .csv export
on takeoff report but I am not aware that what the limitations are now.
Cheers!
------------------------------
Antti Niittyoja
Original Message:
Sent: 02-04-2022 14:39
From: Charlie Sorg
Subject: TBC Material and Site Improvement (MSI) Manager external data
Antti,
Thanks for your question! Can you provide an example of what you would like to be able to import into MSIM? I'd be interested to see that and how it's used in other software so we can better integrate with your workflows.
------------------------------
Charlie Sorg
Product Owner, Trimble Business Center
Civil Design & Engineering
Original Message:
Sent: 01-27-2022 04:23
From: Antti Niittyoja
Subject: TBC Material and Site Improvement (MSI) Manager external data
Hello everybody!
I was wondering that is there a way to have materials and all the data
imported to MSI Manager by (for example) .csv file?
Or is there a way to import other than manually?
Because creating it all by hand and changing the costs takes bit more time.
Our customer also uses those costs in other calculations so they need them
elsewhere so it could be handy if even importing the .csv could be possible.
And maybe later on open API to search data from external data source to
MSI Manager would be great.
Thank you!
------------------------------
Antti Niittyoja
------------------------------