@ Charles
it hard to say with out looking at your project.
do you have any flags? Blue - Multiple Site Improvements per area flag?
Do a Surface Slicer through your areas to verify depths.
Did you apply "Respread" using Identify Site Improvement? Did it leak into another area because it's not closed?
Is the area that shaded correct?
------------------------------
Tim McCann
------------------------------
Original Message:
Sent: 03-17-2022 08:14
From: Charles Wilt
Subject: Take Off bug?
The in-ground demo report for topsoil area is correct but I can't understand why the site-improvement area is 3 times larger. Maybe I am not understanding the difference between these 2 reports.
------------------------------
Charles Wilt
Original Message:
Sent: 03-16-2022 15:36
From: Tim McCann
Subject: Take Off bug?
Charles
Existing Inground Demo volume would be your strip. Does that area and volume sound right for strip?
Site Improvement volume would be Replacement area and volume.
------------------------------
Tim McCann
Original Message:
Sent: 02-28-2022 13:22
From: Charles Wilt
Subject: Take Off bug?
I am working on estimating a project. This site has topsoil removal and replace in different locations. I created these as separate improvements. If I create just the existing in-ground improvement demolition report it says 7148.9 yd2 and 1191.5 yd3 for topsoil removal. If I generate the reports with site improvement quantities then it reports 28221.1 yd2 and 1191.5 yd3 of topsoil removal. Anyone else having similar issues?
------------------------------
Charles Wilt
------------------------------