Hi All,
Im a new user with TBC so im very much still finding my feet with this software.
I have a question regarding combining S9 and R12i data.
I carried out a topo survey with a S9. I have closed-looped the traverse with the S9.
I have also carried out control observations with a R12i to get the correct survey grid and levelled the control points with dumpy level.
Im struggling to combine all the data when processing the data.
How do i apply the the correct coordinates on the control points before using the "adjust traverse" feature?
This is not a quick answer. You will need to spend some time learning, Suggest you start with these:
https://youtu.be/32lSZonnmgg?si=eryfibip7TmY1ohS
https://youtu.be/32lSZonnmgg?si=YDKw3iFkSF9QIW68
There are many power hour webinars and youtube videos from Trimble found on the Community Home tab of this form you posted in. TBC requires the same Point Name used for points when you observe them a second time - either with the same method or by a different method. In the 10 years I've been a TBC user, I've ran 3 traverses and everything else has been Network Adjustment.