Trimble Business Center

 View Only

 Too long...too long waiting for TBC procesess

Luboš Bejček's profile image
Luboš Bejček posted 11-27-2022 14:29
Hey guys

I work with surfaces from drons and I use to create a linestrings for an area where I calculate earthwork reports .....BUT........after I use a line for a calculation (just one), the edit or erase the line freese my work for so, so, so long
now it has been more that an hour I am waiting TBC finish procesing and I just erased a line :((...so I have time to write this post....CAN I avoid this waiting somehow???????

Why is the line linked like that to the earthwork reports???... I want use it more flexibaly.... I know I can duplicate it....BUT.... if I forget it brings me this

Please TBC staff!!...change it!!!!
Marian Plucinski's profile image
Marian Plucinski
Recalculation of your volumes happens because the linestring you used a Boundary is linked to ISOPATCH surface.
Hence evetime you change the linestring, the ISOPATCH is recalculated.

One option would be change properties of the ISOPATCH surface: Rebuild Method, change it to By User.

Also, go to Support -> Options -> Point Clouds and make sure you allocate  50% of your RAM for the surface calcs.
Luboš Bejček's profile image
Luboš Bejček
Thank you Marian

I will try it. I suspected it was related to ISOPATCH. But I dont udesrtand, why the lines as bounderies still use its  role after editing. After editing the line, the report loses its truth, so even the isopath has no meaning and there is no reason why the line should still be connected to it so firmly.

Is it possible to create  "By user" option in general? I suppose not in 5.8. Is it possible to raise this as a request for the next upgrade?