If a surveyor in the field creates a new job and selects copy last setup (from previous job) when i import the new job into TBC it holds the first rod height and prism constant used for the first shot in the resection for all points in the resection. If different heights and constants are used in the resection, this shows the resection values to be off significantly based on the wrong values being computed in TBC. How can i fix this?

Robert Hoy's profile image
Robert Hoy

What's the reason the field surveyor did this?  Using 2 different files on the same day?  

You should be able to change heights, targets through the raw data from project explorer and expanding the JOB file imported.